一, installation and commissioning
1. Before installing the vibration exciter, check the data listed on the nameplate in detail, such as whether the rated voltage, power, speed, excitation force, anchor bolt hole, etc. of the motor meet the requirements;
2. Before starting, you must first confirm that the drive equipment is installed correctly and the exciter can rotate freely;
3. Confirm that the exciter device has been filled with lubricating oil;
4. The fixing bolt of the vibration exciter must be tightened, and the reinforcing spring washer should be prevented from loosening. The fixing bolt will loosen due to the running-in of the fixing bolt and the mounting contact surface at the initial stage of operation. Therefore, the bolt must be tightened again after running for 4 hours. In the first week, tighten once a day, because the small looseness will cause the fixing bolt to break quickly. After one week of operation, the anaerobic adhesive is applied between the bolt and the nut to consolidate it.
二, use and maintenance
1. Since the shaker supplied to the user is installed at the site of use, lubricant should be added after installation.
2. The oil filling position is located at the upper ventilator of the bearing housing. When filling the oil, the ventilator should be removed. Before removing the ventilator, pay attention to cleaning the area around the ventilator.
3. When the vibration device is oiled, the amount of oil is one-third of the volume of the inner cavity, and the excess will increase the temperature of the bearing;
4. Change oil after 50 hours of first run and every 3 months after this run;
5. If the lubricating oil has become dirty or the exciter is working in a high temperature environment, reduce the time interval for oil change so that the final oil change period can be determined according to the field working conditions, and it can be replaced with a better grade of lubricating oil. ;
6. When changing oil, immediately after the shutdown and power supply disconnection, the lubricating oil is discharged from the exciter, and the used oil is discharged before the precipitation occurs, which is beneficial to the injected new oil;
7. The oil drain plug is located under the bearing seat, and a new raw tape seal is required when reinstalling the oil drain plug;
8. Use an infrared thermometer to measure the temperature near the bearing on the end cover and the bearing housing, and the temperature should not exceed 50 degrees when checking the temperature;
9. Note that frequent oil changes and the use of high quality oil will extend the life of the exciter.
三, matters needing attention
1. The vibration absorber provided by Jinte to the user is without lubricating oil. Therefore, the lubricating oil should be added before use.
2. The amount of oil required should not exceed two tooth heights when oil is injected on site.
3. The required oil and viscosity grades depend on the actual operating temperature of the exciter, giving the required lubricant during use of the exciter.
Henan Jinte Vibration Machinery Co.,Ltd has developed into a medium and large international enterprises which specialize in designing and producing screening equipment, vibration equipment and conveying products for complete sets of sand and gravel production lines.
We have professional R&D teams. If u have any concern about equipment, please donot hesitate to contact us. Here is our website site: https://www.hnjinte.com